Islamabad: Today chairman CDA capt (r)Muhammad Usman Younis visited Barakahu bypass project along with Member Engg, Member planning & member Enviroment. PD north NLC & SPM NLC presented the progress of different components of project.
It was apprised that 27 piles out of 32 have been poured at trumpet interchange, 7 piles have been casted at nullah bridge. Casting of girders have been started.
Earth work is also in progress at various locations. Work on elevated portion regarding casting of piles will also be taken up in full swing by tomorrow.
No work is being carried out within QAU boundaries i.e. 1323 meters in compliance with IHC orders.